Interstate Maintenance Closing Lanes Starting Today

Tuesday, February 23rd, 2021

Georgia DOT maintenance forces will repair interstate sections on I-20 and I-520 starting Tuesday, Feb. 23.

Weather permitting the following work will occur.

  • I-20 east mile 184.5 (east of Exit 183) right-hand lane spall repair

    • Single-lane closure in the area for a few hours

    • Spalling concrete means the surface breaks or chips away.

    • This is a one-day operation.

  • I-520 flyover ramp to I-20 concrete joint sealing

    • A separate district crew will add sealant to various locations from the vicinity of Wheeler Road to the I-20 east/westbound ramp split shown below.

    • Expect lane shifts and reduced speed limits in this area during work hours. 

    • Work is set for 9 a.m. to 3 p.m. and could run until Thursday, Feb. 24.